MARSHALL, Mich. (Michigan News Source) – Battery production is underway at one of Michigan’s long-planned megasites.

Battery cells made at Ford’s $3 billion plant in Marshall will power the Fathom electric midsize pickup, which will be built in Louisville. Initial shipments are headed there for use in prototypes.

MORE NEWS: Trump Sign Triggers City Crackdown: Rochester Homeowner Told to Remove It – or Else

Ford says it’s the first U.S. automaker to ship American-made lithium iron phosphate battery cells for mainstream consumer vehicles.

Ford owns and operates the plant, using technology licensed from China-based CATL, the world’s largest battery manufacturer.

The launch at the 2-million-square-foot plant follows community pushback over the Marshall project and other industrial megasites across Michigan.

Millions in taxpayer incentives

State-backed land acquisition efforts for the broader Marshall megasite date to 2018. On Feb. 13, 2023, Ford announced BlueOval Battery Park Michigan, initially proposing a $3.5 billion investment and 2,500 jobs.

Ford briefly paused construction in September 2023 while evaluating whether it could operate the plant competitively. It resumed work that November with a smaller project, reducing projected employment to 1,700 jobs amid slower-than-expected growth in electric vehicle demand. Residents also pursued litigation challenging the site’s rezoning.

In July 2024, the Michigan Strategic Fund approved a revised taxpayer-funded incentive package valued at approximately $384 million to $409 million, including grants and estimated tax benefits. Separate public funding supports megasite land acquisition and infrastructure.

Other Michigan megasites hit roadblocks

MORE NEWS: Flags Lowered for Former Michigan Lawmaker Who Died After Bicycle Struck Sewer Pipe

BlueOval’s production launch comes as other megasite efforts promoted during Gov. Gretchen Whitmer’s tenure have faced setbacks.

Gotion’s proposed battery-component plant in Green Charter Township near Big Rapids collapsed following community opposition, litigation and the withdrawal of state support. Developers stopped pursuing the proposed Eagle Township megasite in Clinton County in 2024.

Meanwhile, Genesee County’s Mundy Township megasite remains without an announced manufacturing tenant after Sandisk abandoned its proposed semiconductor project in 2025.